Stargate Abilene

Stargate is OpenAI's name for its AI data center build-out with Oracle, SoftBank, and other partners. Its flagship site is in Abilene, Texas. Crusoe builds the campus, Oracle runs it on Oracle Cloud Infrastructure (OCI), and OpenAI uses it. OpenAI said in September 2025 that Oracle began delivering the first Nvidia GB200 racks there in June 2025 and that early training and inference had started (OpenAI, 23 Sep 2025).


Key figures

FigureAbilene campus
Buildings8 planned
Floor spaceAbout 4 million sq ft
Power capacity1.2 GW planned
First phase2 buildings, 200+ MW
Second phase6 buildings, expected mid-2026, per Crusoe's March 2025 release
ChipsNvidia GB200 NVL72 racks

A gigawatt (GW) is a billion watts, about the output of one large power plant; a megawatt (MW) is a thousandth of that. Data centers are sized by the power they can draw. Figures are from Crusoe's 18 March 2025 release.

Power and cooling

Crusoe says the site has a 1.2 GW grid connection, plus batteries and solar on site, with natural gas turbines as backup power. Cooling is direct-to-chip liquid cooling in a closed loop that does not evaporate water. Direct-to-chip means cold plates sit on the chips themselves.

What changed

OpenAI's September 2025 post named a possible 600 MW expansion near Abilene. This page does not have a primary source on whether that expansion went ahead.

Other Stargate partners include CoreWeave; see AI cloud providers.